New PROMAGLAS® fire-resistant glazing from Promat

The new PROMAGLAS® system was selected for the refurbishment project of the CCI de Troyes et de l'Aube, both to meet fire safety requirements and for the light and transparency it provides.
An industrial hall with a traditional sawtooth roof has just been refurbished on behalf of the CCI de Troyes et de l'Aube. Built in 1964, the building was formerly a hosiery factory.
?We wanted to preserve the spirit and charm of the place,? says Bernard Figiel, architect at the firm Elleni & Figiel, which has just reconfigured the site, a square of nearly 65 X 65 metres, to create office space for the service sector, subject to public-access building (ERP) regulations.
But the constraints were considerable. The original steel lattice roof structure, which carries the roofing, had no fire stability on the one hand, and on the other hand it was out of the question to add any extra weight. ?We therefore had to do without it and fall back on building a structure beneath it, entirely independent of the roof frame.?
In the end, Bernard Figiel turned this constraint into an aesthetic and functional asset.
Around the perimeter of the hall are the offices: open-plan spaces nearly 15 metres deep, and in the centre large shared areas: meeting rooms and a conference room. Circulation routes 7 metres wide create attractive perspectives for this fluid, contemporary architectural style.
THE FIRE SAFETY REQUIREMENT
To keep this steel lattice roof structure, the original plenum had to be smoke-vented and fire detection had to cover the whole building and the new construction. It was on this condition that it was possible to overcome the roof structure's lack of fire stability and that a waiver from the fire safety regulations was granted.
The all-timber partitioning with ½-hour fire resistance consists of a fir frame incorporating thermal, acoustic and fire insulation, completed with OSB board bracing. On each side of the partition, exposed poplar facings have surfaces treated M1. These partitions are combined with ½-hour fire-resistant PROMAGLAS® glazed frames (fire performance certified by European test reports) from the company Promat. Bernard Figiel recalls the reasons: ?Because the aim was at once to introduce transparency into the construction, to optimise the supply of natural overhead light while preserving some privacy in the spaces created.?
?The glazed partitions were specified by the architect and we did not know this new fire-resistant glazing,? recalls Matthieu Mimey, manager of Lambert menuiserie, a joinery company from the Aube region, over a hundred years old, which managed the works. ?We made the 130 timber frames ourselves, with a density that is stable in fire, and integrated 150 m² of PROMAGLAS® into them without any difficulty. Promat's technical guidelines were clear, with no pitfalls.?
AESTHETICS: THE BIG WINNER
Preserving the spirit and charm of the place was the basic premise, but Bernard Figiel also wanted to contrast with an industrial building whose ?exterior appearance is somewhat hermetic, with an interior that, right from the hall, is much more open, bathed in a soft and pleasant light. The challenge was to express ourselves with a steel frame and a very limited number of materials. The light poplar partitions simply alternate with the PROMAGLAS® glazed volumes. It is a new product that we were fortunate to discover at the right moment.?
The installation of PROMAGLAS® glazed partitions at the CCI de Troyes et de l'Aube proves that, in a quality refurbishment, the most recent construction and fire-prevention technologies can be perfectly integrated into an existing building while meeting architectural requirements.
An industrial hall with a traditional sawtooth roof has just been refurbished on behalf of the CCI de Troyes et de l'Aube. Built in 1964, the building was formerly a hosiery factory.
?We wanted to preserve the spirit and charm of the place,? says Bernard Figiel, architect at the firm Elleni & Figiel, which has just reconfigured the site, a square of nearly 65 X 65 metres, to create office space for the service sector, subject to public-access building (ERP) regulations.
But the constraints were considerable. The original steel lattice roof structure, which carries the roofing, had no fire stability on the one hand, and on the other hand it was out of the question to add any extra weight. ?We therefore had to do without it and fall back on building a structure beneath it, entirely independent of the roof frame.?
In the end, Bernard Figiel turned this constraint into an aesthetic and functional asset.
Around the perimeter of the hall are the offices: open-plan spaces nearly 15 metres deep, and in the centre large shared areas: meeting rooms and a conference room. Circulation routes 7 metres wide create attractive perspectives for this fluid, contemporary architectural style.
THE FIRE SAFETY REQUIREMENT
To keep this steel lattice roof structure, the original plenum had to be smoke-vented and fire detection had to cover the whole building and the new construction. It was on this condition that it was possible to overcome the roof structure's lack of fire stability and that a waiver from the fire safety regulations was granted.
The all-timber partitioning with ½-hour fire resistance consists of a fir frame incorporating thermal, acoustic and fire insulation, completed with OSB board bracing. On each side of the partition, exposed poplar facings have surfaces treated M1. These partitions are combined with ½-hour fire-resistant PROMAGLAS® glazed frames (fire performance certified by European test reports) from the company Promat. Bernard Figiel recalls the reasons: ?Because the aim was at once to introduce transparency into the construction, to optimise the supply of natural overhead light while preserving some privacy in the spaces created.?
?The glazed partitions were specified by the architect and we did not know this new fire-resistant glazing,? recalls Matthieu Mimey, manager of Lambert menuiserie, a joinery company from the Aube region, over a hundred years old, which managed the works. ?We made the 130 timber frames ourselves, with a density that is stable in fire, and integrated 150 m² of PROMAGLAS® into them without any difficulty. Promat's technical guidelines were clear, with no pitfalls.?
AESTHETICS: THE BIG WINNER
Preserving the spirit and charm of the place was the basic premise, but Bernard Figiel also wanted to contrast with an industrial building whose ?exterior appearance is somewhat hermetic, with an interior that, right from the hall, is much more open, bathed in a soft and pleasant light. The challenge was to express ourselves with a steel frame and a very limited number of materials. The light poplar partitions simply alternate with the PROMAGLAS® glazed volumes. It is a new product that we were fortunate to discover at the right moment.?
The installation of PROMAGLAS® glazed partitions at the CCI de Troyes et de l'Aube proves that, in a quality refurbishment, the most recent construction and fire-prevention technologies can be perfectly integrated into an existing building while meeting architectural requirements.